Land Area Converter
Convert land area between Ropani-Anna-Paisa-Dam, Bigha-Kattha-Dhur, and standard units.
Formula: Dry = 1.54 × wet; split by ratio shares · 2 inputs · step-by-step working
Quickly translate a concrete pour into cement bags plus sand and coarse aggregate volumes.
Enter the desired wet volume in m³ and the mix ratio (cement : sand : aggregate).
Enter the volume of finished (wet) concrete in cubic metres and a three-part mix ratio. The calculator multiplies the wet volume by 1.54 to get the dry volume of loose materials, then splits that dry volume by the ratio. For 1:1.5:3 the parts add up to 5.5, so cement takes 1/5.5 of the dry volume, sand 1.5/5.5 and aggregate 3/5.5.
Cement is converted to bags using a density of 1,440 kg/m³ and 50 kg per bag, so one bag is about 0.0347 m³. Sand and aggregate are shown in cubic metres; multiply by 35.31 if your supplier quotes in cubic feet. Water is not included, because the right amount depends on the cement, how wet the sand and aggregate are, and the workability needed on site. The figures have no waste allowance, so add 5 to 10% before ordering; 10% is safer for a first build or a hand-mixed pour.
| Mix (cement : sand : aggregate) | Nominal grade | Cement (50 kg bags) | Sand (m³) | Aggregate (m³) |
|---|---|---|---|---|
| 1 : 1 : 2 | M25 | 11.1 | 0.39 | 0.77 |
| 1 : 1.5 : 3 | M20 | 8.1 | 0.42 | 0.84 |
| 1 : 2 : 4 | M15 | 6.3 | 0.44 | 0.88 |
| 1 : 3 : 6 | M10 | 4.4 | 0.46 | 0.92 |
The number after M is the characteristic compressive strength in N/mm² after 28 days of curing. Structural members such as columns, beams and slabs should use the grade on your structural drawings.
Work out the wet volume as length × width × thickness in metres, enter it with the mix, then add your waste allowance to the result.
| Job | Size | Wet volume | Mix | Cement | Sand | Aggregate |
|---|---|---|---|---|---|---|
| House floor slab | 20 ft × 15 ft × 4 in | 2.83 m³ | 1:1.5:3 | 22.8 bags | 1.19 m³ (about 42 cu ft) | 2.38 m³ (about 84 cu ft) |
| Pathway or driveway | 10 m × 2 m × 100 mm | 2 m³ | 1:2:4 | 12.7 bags | 0.88 m³ (about 31 cu ft) | 1.76 m³ (about 62 cu ft) |
| Square column | 0.3 m × 0.3 m × 3 m | 0.27 m³ | 1:1.5:3 | 2.2 bags | 0.11 m³ | 0.23 m³ |
With a 10% allowance the floor slab needs 22.8 × 1.1 = 25.1, so order 26 bags of cement and about 10% more sand and aggregate than shown.
These are material estimates only. Foundations, columns, beams and slabs need a structural design that meets Nepal’s National Building Code, prepared and supervised by a licensed engineer.
Convert land area between Ropani-Anna-Paisa-Dam, Bigha-Kattha-Dhur, and standard units.
Number of bricks for a wall, with mortar volume estimate.
Plan ground-up house construction cost in Nepal by plot size, floors, coverage and finish quality — with phase-wise breakdown.